Downtown Boca Raton's New Condos, Sorted by How Far Along They Are

  • November 19, 2026

At 280 East Palmetto Park Road, Glass House Boca Raton went vertical this summer. At 41 Southeast 4th Street, the Mr. C Residences won approval for a revised site plan from the city's Community Redevelopment Agency on Oct. 26. On Southeast Mizner Boulevard, the ALINA 210 and 220 towers are finished, with residents in 210 and closings underway at 220. At 105 East Camino Real, construction on the Mandarin Oriental Residences was reported underway in 2019, and the project is now in court.

The Real Deal describes downtown Boca as attracting "a spree of luxury condo developments," and from the sidewalk it reads as one wave. For a buyer, these are four different purchases. Each project has reached a different point between rendering and closing, and the price at each point pays for a different amount of proof. Finished towers sell against recorded closings. A building under construction sells against a construction loan and a schedule. A presale sells against a brand, an approved plan and a sales pace. What a buyer is really choosing is how much of the project they want settled before they sign.

ALINA: finished, and priced against its own closings

El-Ad National Properties' ALINA is the only one of the four with a full sales record. The first tower, ALINA 200, was completed in March 2021. Phase Two is 182 homes: 30 in ALINA 210 and 152 in ALINA 220. ALINA 210 received its final certificate of occupancy in 2024, and ALINA 220 received a temporary certificate of occupancy on Jan. 9, 2025, with closings starting after that, BocaPost reported in April 2026. The same report put Phase Two pricing at just over $6 million to more than $9 million as of April 23, 2026, for homes of one to four bedrooms and roughly 1,400 to more than 5,400 square feet. It also credited the developer with more than $60 million in sales over the 2026 winter and spring, three penthouses among them.

At this stage the buyer can compare the price to actual closings. In spring 2025 those closings covered a wide range. During the week of April 6 to 13, 2025, ALINA 220 unit 321 closed at $3.5 million, or $1,270 a square foot, according to The Real Deal's Palm Beach County condo report. El-Ad announced the $10 million sale of Penthouse 903 at ALINA 210 on April 15, 2025. That home has 5,394 interior square feet, which works out to roughly $1,854 a square foot before counting its 1,206-square-foot terrace. In June 2025, The Real Deal reported a $6.5 million purchase of a 4,265-square-foot ALINA 220 unit, about $1,524 a square foot of interior space.

That spring 2025 range is useful context. In the same April 2025 weekly report, unit 6S at 750 Ocean in Boca Raton closed at $4.15 million, or $1,497 a square foot. A finished downtown tower and an ocean-side building were selling in the same per-foot range that week. Brand-new construction did not put a home in a price tier of its own. What ALINA's price mostly covers is certainty, because the towers are built and have a sales history a buyer can price against.

Glass House: under construction, and priced from a published range

One stage behind ALINA is Glass House Boca Raton, at 280 East Palmetto Park Road. It is a nine-story building with 28 residences of two to four bedrooms, from 2,504 to 3,865 square feet. As of March 9, 2026, Multi-Housing News reported prices of $2.7 million to $8 million. The project broke ground in April 2025 and has a $70 million construction loan. Each residence comes with two parking spaces, and the amenities include a rooftop pool with cabanas, a fitness center, a sauna and a steam room. The developer announced on June 1, 2026 that vertical construction had begun and projected completion in the fourth quarter of 2027.

A Glass House buyer can see a lender's commitment and a building going up. What they can't see yet is a closing at the address. The schedule has also moved before. Florida YIMBY's 2024 report projected completion in fall 2026, and the current target is about a year later. A year's change on a project with a loan in place is normal. It also means a buyer at this stage is paying today's price for a home they will move into at least one season from now.

Mr. C Residences: a presale, priced on a brand and a pace

Wexford Real Estate Investors and Key International bought the 2.1-acre site at 41 Southeast 4th Street for $25.5 million in 2023 and announced a partnership with the Cipriani family's Mr. C brand in January 2026, according to The Real Deal. The plan is a 12-story building designed by Arquitectonica, with a 6,000-square-foot Bellini restaurant, a pickleball court and a dog park. Units start at about $2.2 million, and half were sold in the first six months of sales, according to the developers' news release.

The developers asked the city to cut the project from 190 units to 133, enlarge the building and its parking garage, and add the restaurant space. City records list the application as "The Residences of Boca," and the CRA approved the amendment 4–0 on Oct. 26, 2026.

About $2.2 million is the lowest starting price among the three projects with current pricing. It also buys the least that a buyer can check today. The evidence is a known hospitality brand, a well-known architect, a plan the city approved a month ago and a 50 percent presale pace. A contract here holds a spot in a building whose revised plan is only weeks old. Buyers who choose this stage are taking the lower entry price in exchange for the longest wait and the most open questions.

The Mandarin Oriental Residences: when a stage lasts longer than planned

The fourth address shows that the time between contract and closing can grow. Penn-Florida announced the Mandarin Oriental-branded hotel and condominium at Camino Real in 2015. A 2017 report projected the hotel would be finished toward the end of 2019 and the residences in 2020. Condo construction was reported underway by July 2019.

In July 2026, a lender group filed a $417.7 million foreclosure suit that alleges, among other things, that the project missed a February 2025 completion deadline, The Real Deal reported. The same report said 13 buyers had sued over delayed deliveries, one buyer had won a $1.98 million judgment, another had settled for $2.1 million, and most deposits had been released to help fund construction. In August, the developer's affiliates sued in New York, alleging the lender created the defaults it was using to foreclose. On Oct. 1, a New York state court ruled that the lender could not seize and sell collateral for the project's $418 million loan, the Palm Beach Post reported.

The project's latest reported plan is 88 condominiums. Every project goes through a stage between a signed contract and a certificate of occupancy. This address shows how long that stage can last, and that is part of what a presale price is pricing.

Reading the starting prices together

Put the starting prices side by side and the order looks backward. The presale at Mr. C starts around $2.2 million. Glass House, under construction, starts at $2.7 million. ALINA's finished Phase Two was priced from just over $6 million this spring. Home sizes differ too much across the three for a clean per-foot comparison. What the order does show is that the lower figures come with the most unsettled questions: when the building will be delivered, what it will look like when finished, and what similar homes in it will actually sell for.

ALINA's spring 2025 closings answer those questions with recorded prices, from $1,270 to roughly $1,854 a square foot. Glass House can point to a construction loan and a fourth-quarter 2027 target, while Mr. C has a 4–0 vote and a sales pace behind it. If you're comparing new construction in this part of town, start by deciding which of those kinds of proof you need in hand before you sign, then look at the price.

Common questions

Is "The Residences of Boca" in city records the same project as the Mr. C Residences? Yes. The CRA application covers the same 2.1-acre site at 41 Southeast 4th Street and the same reduction from 190 to 133 units described in The Real Deal's coverage of the Mr. C project.

Is the Boca Raton Mandarin Oriental project connected to the Mandarin Oriental condo planned in West Palm Beach? No. The Palm Beach Post reported that the Boca Raton project is not affiliated with the planned West Palm Beach Mandarin Oriental condominium.

Where can I read more about this part of Boca? Our Southeast Boca Raton neighborhood page covers the area. Our post on the Federal Highway lane change south of Mizner covers the street work around Camino Real, and Understanding Luxury Condo Fees in Boca Raton explains what monthly fees cover once you own a condo.

The prices in this post are reported figures with their dates. They are general information, not legal or financial advice, so confirm any contract terms with your own attorney and lender before you sign.

If you're deciding between a finished downtown tower and a contract on one still in progress, Judith Randon Realty can help you set the recorded closings in the finished buildings beside the presale terms you've been offered. If an existing condo would fund the move, start with a free home valuation and consultation so you know what your current home is worth before you choose a stage.